Crawfordsburn Diary Entry No.21 - Coming to an End

Crawfordsburn Diary Entry No.21 - Coming to an End

The Crawfordsburn passive house is in the final phase of works, the internal plastering and external rendering are now complete. The bathrooms and kitchen are being installed, as are internal doors and the glazed internal balcony.

Read More
Crawfordsburn Diary Entry No.19 - Ventilation (MVHR)

Crawfordsburn Diary Entry No.19 - Ventilation (MVHR)

The ventilation system, with heat recovery, is an integral component of the dwelling, essential for achieving the Passivhaus certification performance levels.  A proven low-energy and highly efficient ventilation method, MVHR is fast becoming the most common method of whole home ventilation for new build properties

Read More
Crawfordsburn Diary Entry No.18 - Achieving Airtightness

Crawfordsburn Diary Entry No.18 - Achieving Airtightness

The airtightness, as already mentioned in previous diary entries, is crucial for the overall success of the passive house. We have discussed the high risk air leakage components such as wall openings, floor-to-wall junctions and wall-to-roof junctions.

Read More
Crawfordsburn Diary Entry No.17 - The Roof

Crawfordsburn Diary Entry No.17 - The Roof

The build has continued to proceed well; it is very exciting seeing each step of construction completed. The snow arrived on site recently making the working conditions rather cold for the construction team! Many sub-contractors are starting to appear on site to play their part in various installations

Read More
Crawfordsburn Diary Entry No.15 - Windows and Doors

Crawfordsburn Diary Entry No.15 - Windows and Doors

All windows and doors utilised in Passivhaus certified buildings have to meet certain performance criteria. The wall openings have been discussed in the previous diary entry but here we will detail the exact capabilities of the window and doors units.

Read More
Crawfordsburn Diary Entry No.14 - The Wall Openings

Crawfordsburn Diary Entry No.14 - The Wall Openings

After a slight delay, this week saw the installation of the windows and doors in the Crawfordsburn passive house. We have decided to use this diary entry to address how we’ve dealt with the window and door openings. In the next entry we will discuss the specific window and door units. 

Read More
Crawfordsburn Diary Entry No.13 - The Timber Frame Construction

Crawfordsburn Diary Entry No.13 - The Timber Frame Construction

In the last diary entry we announced that the timber frame construction kit had arrived on site. In the past two weeks it has transformed from individuals panels into an actual dwelling. It has been fantastic to witness and we feel like the build is really starting to take shape now.

Read More
Crawfordsburn Diary Entry No.12 - The Timber Frame

Crawfordsburn Diary Entry No.12 - The Timber Frame

So the big day is here, the timber frame kit has finally arrived! We will have lots of photos documenting the frame as it is erected over the next few weeks, so keep your eyes peeled. For now the photograph below shows the frame unloaded on to the site ready for construction to commence tomorrow.

Read More
Crawfordsburn Diary Entry No.11 - The Waiting Game

Crawfordsburn Diary Entry No.11 - The Waiting Game

We spoke too soon when we boasted about everything running on time! This week marked the start of the waiting game ... SIPFIT our timber frame manufacturer is running slightly behind schedule so were anxiously awaiting the arrival of the SIP Panels which should be any day now, fingers crossed.  

Read More
Crawfordsburn Diary Entry No.9 - Thermal Block Installation

Crawfordsburn Diary Entry No.9 - Thermal Block Installation

The product utilised for this construction is Foamglas® Perinsul.  Foamglas® Perinsul is a very high density speciality product used to eliminate structural thermal bridging. All sides are bitumen coated. The upper and the lower surface of the insulation are additionally coated with glass reinforced fleece.

Read More
Crawfordsburn Diary Entry No.8 - Thermal bridging

Crawfordsburn Diary Entry No.8 - Thermal bridging

As previously discussed we had identified two independent timber companies that could supply the timber construction kit for the Crawfordsburn passive house. As the two systems have slight differences we have had to alter some of our drawings to suit the selected panels. 

Read More
Crawfordsburn Diary Entry No.6 - On Site Commences

Crawfordsburn Diary Entry No.6 - On Site Commences

After an intensive year of research, design and planning the Crawfordsburn passive house is now ready for construction to commence. The design process, extensive Passivhaus calculations, planning application, building control application and contract tender process are now all complete.

Read More