Crawfordsburn Diary Entry No.13 - The Timber Frame Construction

Crawfordsburn Diary Entry No.13 - The Timber Frame Construction

In the last diary entry we announced that the timber frame construction kit had arrived on site. In the past two weeks it has transformed from individuals panels into an actual dwelling. It has been fantastic to witness and we feel like the build is really starting to take shape now.

Read More
Crawfordsburn Diary Entry No.12 - The Timber Frame

Crawfordsburn Diary Entry No.12 - The Timber Frame

So the big day is here, the timber frame kit has finally arrived! We will have lots of photos documenting the frame as it is erected over the next few weeks, so keep your eyes peeled. For now the photograph below shows the frame unloaded on to the site ready for construction to commence tomorrow.

Read More
Crawfordsburn Diary Entry No.11 - The Waiting Game

Crawfordsburn Diary Entry No.11 - The Waiting Game

We spoke too soon when we boasted about everything running on time! This week marked the start of the waiting game ... SIPFIT our timber frame manufacturer is running slightly behind schedule so were anxiously awaiting the arrival of the SIP Panels which should be any day now, fingers crossed.  

Read More