Crest Diary Entry No.13 – Final Finishes
The CREST Pavilion is now handed over to the client, South West College. All the building works are complete and external grassing and landscaping is being left until the planting season.
Crest Diary Entry No.10 – Air tightness testing
The air tightness, as already mentioned in previous diary entries, is crucial for the overall success of the building and for achieving the stringent passive house standards that were set at the outset of the project. In previous diary entries, we have discussed the high risk air leakage components such as wall openings, floor-to-wall junctions
Crest Diary Entry No.9 - Fitting of the Zinc Roof
Since our last article, the majority of the windows and doors in the external envelope have been fitted, and the zinc roofing has commenced, with the roof over the renewable technologies roof nearly complete.